Get email notifications whenever Statuspage Netrics Zürich AG creates, updates or resolves an incident.
Get webhook notifications whenever Statuspage Netrics Zürich AG creates an incident, updates an incident, resolves an incident or changes a component status.
Completed -
The scheduled maintenance has been completed.
Apr 15, 02:00 CEST
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Apr 14, 18:00 CEST
Scheduled -
Interxion will be performing maintenance work on the UPS Output Breakers in ZRH1.3 / 1.4 (UPS3 and UPS4). The UPS3 breakers will be serviced on April 13th and the UPS4 breakers on April 14th. During this maintenance, one power feed to your Equipment will be powered OFF, so this means that your equipment is only powered via one feed. After one feed is maintained we will be put back into normal operation. On the following day, the same process will be applied to the opposite feed
Interxion would like you to make sure that your equipment it is powered from two different feeds. During these two days it is also recommended for you to have your technicians on site to closely monitor your equipment.
Interxion has planned the following time slots for the maintenance:
14 April 2021 06:00 p.m. switch off the UPS4 output breaker ZRH1_U_MDB_ 62_12_UPSsec. / Return to normal operation at around 08:00 p.m. 08:30 p.m. switch off the UPS4 output breaker ZRH1_U_MDB_ 62_13_UPSsec. / Return to normal operation at around 10:30 p.m. 00:00 a.m. switch off the UPS4 output breaker ZRH1_U_MDB_ 62_14_UPSsec. / Return to normal operation at around 02:00 a.m.
Apr 13, 18:00 CEST
Completed -
The scheduled maintenance has been completed.
Apr 14, 02:01 CEST
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Apr 13, 18:45 CEST
Scheduled -
Interxion will be performing maintenance work on the UPS Output Breakers in ZRH1.3 / 1.4 (UPS3 and UPS4). The UPS3 breakers will be serviced on April 13th and the UPS4 breakers on April 14th. During this maintenance, one power feed to your Equipment will be powered OFF, so this means that your equipment is only powered via one feed. After one feed is maintained we will be put back into normal operation. On the following day, the same process will be applied to the opposite feed
Interxion would like you to make sure that your equipment it is powered from two different feeds. During these two days it is also recommended for you to have your technicians on site to closely monitor your equipment.
Interxion has planned the following time slots for the maintenance:
13 April 2021 06:00 p.m. switch off the UPS3 output breaker ZRH1_U_MDB_ 61_12_UPSsec. / Return to normal operation at around 08:00 p.m. 08:30 p.m. switch off the UPS3 output breaker ZRH1_U_MDB_ 61_13_UPSsec. / Return to normal operation at around 10:30 p.m. 00:00 a.m. switch off the UPS3 output breaker ZRH1_U_MDB_ 61_14_UPSsec. / Return to normal operation at around 02:00 a.m.
Apr 13, 18:37 CEST
The temperature has now stabilized and returned within the normal parameters.
A full incident report will follow.
Apr 6, 13:49 CEST
Identified -
During the scheduled power breaker maintenance, the cooling system has failed. The emergency cooling system has taken over, temperatures are higher, but within specifications. We will update this report as soon as we have further information about the reason, duration and resolution.
Apr 6, 11:26 CEST