Interxion GLB2: UPS Output Breakers in ZRH1.3 / 1.4 (UPS3 and UPS4). Scheduled Maintenance.
Scheduled Maintenance Report for Statuspage Netrics Zürich AG
Completed
The scheduled maintenance has been completed.
Posted Apr 15, 2021 - 02:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 14, 2021 - 18:00 CEST
Scheduled
Interxion will be performing maintenance work on the UPS Output Breakers in ZRH1.3 / 1.4 (UPS3 and UPS4). The UPS3 breakers will be serviced on April 13th and the UPS4 breakers on April 14th. During this maintenance, one power feed to your Equipment will be powered OFF, so this means that your equipment is only powered via one feed. After one feed is maintained we will be put back into normal operation. On the following day, the same process will be applied to the opposite feed

Interxion would like you to make sure that your equipment it is powered from two different feeds. During these two days it is also recommended for you to have your technicians on site to closely monitor your equipment.

Interxion has planned the following time slots for the maintenance:

14 April 2021
06:00 p.m. switch off the UPS4 output breaker ZRH1_U_MDB_ 62_12_UPSsec. / Return to normal operation at around 08:00 p.m.
08:30 p.m. switch off the UPS4 output breaker ZRH1_U_MDB_ 62_13_UPSsec. / Return to normal operation at around 10:30 p.m.
00:00 a.m. switch off the UPS4 output breaker ZRH1_U_MDB_ 62_14_UPSsec. / Return to normal operation at around 02:00 a.m.
Posted Apr 13, 2021 - 18:00 CEST
This scheduled maintenance affected: Datacenter Service Glattbrugg.